HOW TO CALCULATE CEMENT BAGS IN 1 CUBIC METER


PROCEDURE TO CALCULATE CEMENT BAGS IN 1 CUBIC METER:

Let us consider the nominal mix is 1:2:4
Loss of cement is considered as 2%
Output of mix is considered as 67%


To achieve 1 cum output,
we need 1/0.67 = 1.49 say 1.50 cum dry mix.
Now add the wastage of 2%, i.e (1.50 + 0.02) = 1.52 cum.
Volume of cement = (cement/cement+sand+aggregate) × Total material =(1/1+2+4) × 1.52
=0.2171 cum

As we know, the density of cement is 1440 kg/cum and

Weight of 1 bag cement = 50 kg.
Therefore volume of 1 bag cement = 50/1440
   = 0.0347 cum.
 No. of cement bags required in 1 cubic meter =       

     0.2171/0.0347= 6.25 bags.